Development of Autonomous Cable Inspection Robot for Nuclear Power Plant

The cables in a nuclear power plant are designed to be used for about 40 years in safe operation environment. However, the heat and radiation in the nuclear power plant causes the rapid performance deterioration of cables in nuclear vessels and heat exchangers, which requires cable lifetime estimation. The most accurate method of estimating the cable lifetime is to evaluate the cables in a laboratory. However, removing cables while the plant is operating is not allowed because of its safety and cost. In this paper, a robot system to estimate the cable lifetime in nuclear power plants is developed and tested. The developed robot system can calculate a modulus value to estimate the cable lifetime even when the nuclear power plant is in operation.

Development of Condition Monitoring System with Control Functions for Wind Turbines

As an effort to promote wind power industry in Korea, Korea South-East Power Corporation has been developing 22MW YeungHeung wind farm consisting of nine 2 to 3MW wind turbines supplied by three manufacturers. To maximize its availability and reliability and to solve the difficulty of operating three kinds of SCADA systems, Korea Electric Power Corporation has been developing a condition monitoring system integrated with control functions. This paper presents the developed condition monitoring system and its application to YeungHeung wind test bed, and the design of its control functions.

Development of Wind Turbine Simulator for Generator Torque Control

Wind turbine should be controlled to capture maximum wind energy and to prevent the turbine from being stalled. To achieve those two goals, wind turbine controller controls torque on generator and limits input torque from wind by pitching blade. Usually, torque on generator is controlled using inverter torque set point. However, verifying a control algorithm in actual wind turbine needs a lot of efforts to test and the actual wind turbine could be broken while testing a control algorithm. So, several software have developed and commercialized by Garrad Hassan, GH Bladed, and NREL, FAST. Even though, those programs can simulate control system modeling with subroutines or DLLs. However, those simulation programs are not able to emulate detailed generator or PMSG. In this paper, a small size wind turbine simulator is developed with induction motor and small size drive train. The developed system can simulate wind turbine control algorithm in the region before rated power.