Abstract: The Resource-Constrained Project Scheduling
Problem (RCPSP) is concerned with single-item or small batch
production where limited resources have to be allocated to dependent
activities over time. Over the past few decades, a lot of work has
been made with the use of optimal solution procedures for this basic
problem type and its extensions. Brucker and Knust[1] discuss, how
timetabling problems can be modeled as a RCPSP. Authors discuss
high school timetabling and university course timetabling problem as
an example. We have formulated two mathematical formulations of
course timetabling problem in a new way which are the prototype of
single-mode RCPSP. Our focus is to show, how course timetabling
problem can be transformed into RCPSP. We solve this
transformation model with genetic algorithm.