Genetic Algorithms Multi-Objective Model for Project Scheduling

Time and cost are the main goals of the construction
project management. The first schedule developed may not be a
suitable schedule for beginning or completing the project to achieve
the target completion time at a minimum total cost. In general, there
are trade-offs between time and cost (TCT) to complete the activities
of a project. This research presents genetic algorithms (GAs) multiobjective
model for project scheduling considering different
scenarios such as least cost, least time, and target time.


Authors:



References:
[1] Liu, L., Burns, S., and Feng, C., “Construction Time-Cost Trade-Off
Analysis Using LP/IP Hybrid Method,” Journal of Construction
Engineering and Management, ASCE, 121(4), 446-454, 1995.
[2] Maghrebi, M., Afshar, A., and Maghrebi, M. J., “A Novel Mathematical
Model for Deterministic Time-cost Trade-off Based on Path Constraint,”
International Journal of Construction Engineering and Management
2(5): 137-142, 2013.
[3] Zheng, D., Ng, S. T., and Kumaraswamy, M., “Applying a Genetic
Algorithm-Based Multiobjective Approach for Time-Cost
Optimization,” Journal of Construction Engineering and Management,
ASCE, 130(2), 168-176, 2004.
[4] Forrest, S., “Genetic Algorithms: Principles of Natural Selection
Applied to Computation”, Science 261, 1993.
[5] Feng, C., Liu, L., and Burns, S., “Using genetic algorithms to solve
construction time–cost trade-off problems,” ASCE Journal of
Computing in Civil Engineering, 11(3), 184–189, 1997.
[6] Li, H., Cao, J.-N., and Love, P., “Using Machine Learning and GA to
Solve Time-Cost Trade-Off Problems,” Journal of Construction
Engineering and Management, ASCE, 125(5), 347-353, 1999.
[7] Hegazy, T., “Optimization of construction time–cost trade-off analysis
using genetic algorithms,” Canadian Journal of Civil Engineer Vol. 26,
685–697, 1999.
[8] Ammar, M. A., “Optimization of project time-cost trade-off problem
with discounted cash flows,” Journal of Construction Engineering and
Management, 137(1), 65-71, 2010.
[9] Aghassi, H., et al., “a multi-objective Genetic Algorithm for
optimization time-cost trade-off scheduling,” Knowledge Technology,
Springer, 356-359, 2012.
[10] Ghoddousi, P., et al., “Multi-mode resource-constrained discrete time–
cost-resource optimization in project scheduling using non-dominated
sorting genetic algorithm,” Automation in Construction, 216–227, 2013.
[11] Bettemir, Ö.H., “Experimental Design for Genetic Algorithm Simulated
Annealing For Time Cost Trade-Off Problems,” International Journal of
Engineering & Applied Sciences (IJEAS) Vol.3, Issue 1, 15-26, 2011.