Abstract: This paper provides some thoughts about the lack of
attentiveness of building commissioning in the construction industry
and the lack of handling in project commissioning as an integral part
of the project life-cycle. Many have perceived commissioning as the
problem solving process of a project, rather than the start up of the
equipment, or the handing over of the project to the client. Therefore,
there is a lack of proper attention in the planning of commissioning
as a vital part of the project life-cycle. This review paper aims to
highlight the benefits of building commissioning and to propose the
lacking of knowledge gap on building commissioning. Finally, this
paper hopes to propose the shift of focus on this matter in future
research.
Abstract: The purpose of this study is to identify the underlying
causes of late payment from the contractors- perspective in the
Malaysian construction industry and to recommend effective solutions
to mitigate late payment problems. The target groups of respondents in
this study were Grades G3, G5, G6 and G7 contractors with
specialization in building works and civil engineering works registered
with the Construction Industry Development Board (CIDB) in
Malaysia. Results from this study were analyzed with Statistical
Package for the Social Science (SPSS 15.0). From this study, it was
found that respondents have highest ranked five significant variables
out of a total of forty-one variables which can caused late payment
problems: a) cash flow problems due to deficiencies in client-s
management capacity (mean = 3.96); b) client-s ineffective utilization
of funds (mean = 3.88); c) scarcity of capital to finance the project
(mean = 3.81); d) clients failure to generate income from bank when
sales of houses do not hit the targeted amount (mean=3.72); and e)
poor cash flow because of lack of proper process implementation,
delay in releasing of the retention monies to contractor and delay in the
evaluation and certification of interim and final payment (mean =
3.66).